‎First Avenue issues updates on projects progress

‎First Avenue issues updates on projects progress ‎First Avenue issues updates on projects progress

​‎

Logo ofFirst Avenue for Real Estate Development Co.

First Avenue for Real Estate Development Co. issued today, Feb. 10, a report on the progress of executing its projects and completion rates.

Advertisement

This comes in line with the company’s efforts to enhance transparency and develop its disclosure framework, and in its commitment to keeping investors and shareholders continuously informed about its business developments and financial performance, the company said, in a statement to Tadawul.

This report will be continuously improved to include more information that aligns with shareholder expectations and strengthens disclosure and transparency practices. The company aims to publish this report on a quarterly basis

The table below shows updates on the company’s projects and completion rates. It noted that four projects are 100% complete, two (99%) and another project 74% complete.

Summary of the Company’s Projects

Project

Type of Project

Leasing/Selling Space (sqm)

Completion%

Business Avenue (Al-Kairawan)

Office

11180

18%

Business Avenue (Cordova)

Office

11727

74%

Al Mohammadia Avenue

Office/residential/ Commercial

9451

30%

Diriyah Avenue

Residential

31511

43%

La Perle Residental – Al Nakheel

Residential

7493

100%

Al Basateen Avenue

Residential/ Commercial

46082

La Perle residential tower

Residential

La Perle East

Commercial – Office

11165

99%

La Perle West

Commercial – Office

5679

99%

Al Shorfa Al Majidia

Commercial – Office

5900

100%

Malka Tital Al Riyadh

Residential

10300

100%

Palm Avenue 119

Residential

16028

100%

 

Logo ofFirst Avenue for Real Estate Development Co.

First Avenue for Real Estate Development Co. issued today, Feb. 10, a report on the progress of executing its projects and completion rates.

This comes in line with the company’s efforts to enhance transparency and develop its disclosure framework, and in its commitment to keeping investors and shareholders continuously informed about its business developments and financial performance, the company said, in a statement to Tadawul.

This report will be continuously improved to include more information that aligns with shareholder expectations and strengthens disclosure and transparency practices. The company aims to publish this report on a quarterly basis

The table below shows updates on the company’s projects and completion rates. It noted that four projects are 100% complete, two (99%) and another project 74% complete.

Summary of the Company’s Projects

Project

Type of Project

Leasing/Selling Space (sqm)

Completion%

Business Avenue (Al-Kairawan)

Office

11180

18%

Business Avenue (Cordova)

Office

11727

74%

Al Mohammadia Avenue

Office/residential/ Commercial

9451

30%

Diriyah Avenue

Residential

31511

43%

La Perle Residental – Al Nakheel

Residential

7493

100%

Al Basateen Avenue

Residential/ Commercial

46082

La Perle residential tower

Residential

La Perle East

Commercial – Office

11165

99%

La Perle West

Commercial – Office

5679

99%

Al Shorfa Al Majidia

Commercial – Office

5900

100%

Malka Tital Al Riyadh

Residential

10300

100%

Palm Avenue 119

Residential

16028

100%

Add a comment

Leave a Reply

Your email address will not be published. Required fields are marked *

Keep Up to Date with our Weekly Newsletter

By pressing the Subscribe button, you confirm that you have read and are agreeing to our Privacy Policy and Terms of Use
Advertisement